Skip to content

Execution, operation and close out

share icon

Who is this for?

Major customers that have completed the Planning stage and have an executed Access Offer.

clock icon

How long will it take?

 Project specific  

dollar icon

How much will it cost?

Project specific

Connection process

 
5
Execution

During this stage we will complete the dynamic network studies, detailed design, procurement, construction and commissioning of the required network modifications and your facility (as applicable) under the terms of your Interconnection Works Contract (IWC).

Pre-Construction Activities

Below are the indicative costs and timings for each of the pre-construction activities that may be required: 

  Activity   Estimated cost*   Estimate timeframe* Customer inputs/deliverables required  
Dynamic Studies - RMS Networks   $55,000 (excluding GST)   10 weeks
  • Access Offer contracts (IWC and ETAC) executed, and payment/securities received  
Stage 1: EMT Studies (SMIB)   $30,000 (excluding GST)   5 weeks
  • Access Offer contracts (IWC and ETAC) executed, and payment/securities received
  • Updated Connection Application
  • PSCAD Model
  • Model User Guide
Stage 2: EMT Studies (Networks)   $55,000 (excluding GST)   10 weeks
  • Access Offer contracts (IWC and ETAC) executed, and payment/securities received
  • Updated Connection Application
  • PSCAD Model
  • Model User Guide
Detailed Design   Project specific Project specific
  • Access Offer contracts (IWC and ETAC) executed, and payment/securities received  

Construction and Commissioning

Below are the high-level activities and customer inputs/deliverables required: 

  Activity   Estimated cost*   Estimate timeframe* Customer inputs/deliverables required  
Procurement and Construction (including GPS Assessment R1 Validation - Generation only)     Project Specific   Project Specific  
Access Offer contracts (IWC and ETAC) executed and all IWC customer deliverables have been satisfied, these may include:
 
  • Final studies and designs completed
  • Financial close achieved (payment or securities received)
  • All land access agreements are in place
  • All easements have been agreed
  • All Environmental, Planning and Heritage Approvals have been provided
  • All third-party approvals (gas, water, railway, telecommunications etc.) provided
  • GPS R1 assessment submission (Generation only)

Non-thermal Limits Equation Study

Up to $40,000     Up to 8 weeks  
  • Latest confirmed model fo the customers facility 

Commissioning (including GPS Assessment R2 Validation - Generation only)

Project Specific     Project Specific  
  • For market participant generators a Commissioning Test Plan, which documents commissioning tests to be performed, must be approved by AEMO in advance of any testing.

Operation and Close Out

Once constructed and commissioned, the new or modified connection assets can begin operating under the terms of the Electricity Transfer Access Contract (ETAC) and we can formally close out your project.

For generators, operation is subject to receiving an Approval to Generate Notification, in accordance with the WEM Rules.

  Activity   Estimated cost*   Estimate timeframe* Customer inputs/deliverables required  
Project close out     $10,000 (excluding GST)   Up to 12 months  
  • Nil

*The estimated costs and timeframes shown above are to be used as a guide and will vary depending on project specifics, such as facility size, connection voltage, complexity and geographic etc. The durations are based on all customer deliverables having been received and with no queuing time. Some activities may be able to happen in parallel.